Date Booked
01/11/22
Project Type
Int
Start Date
01/19/22
Deadline
04/11/22
Total amount
$7740
Amount Payed To Date
$5000
Amount Still Owed
$2774
Estimate
View estimate
01/23/23
Work Order Summary
| Work Orders | Start | End | Total | Expenses | Status | Daily Log | Punch List | Check by | Action |
|---|---|---|---|---|---|---|---|---|---|
|
Int painting 001 Work Order 1047 |
6/21/23
|
7/1/23 |
$456 | Add |
|
Zac Lee | |||
|
Ext painting 001 Work Order 1047 |
6/21/23
|
7/1/23 |
$206 |
$30 |
|
Zac Lee | |||
|
Carpentry 001 Work Order 1047 |
6/21/23
|
7/1/23 |
$56 |
Add |
|
Zac Lee | |||
|
Power washing 001 Work Order 1047 |
6/21/23
|
7/1/23 |
$56 |
< Add |
|
Zac Lee | |||
|
Int painting 002 Work Order 1047 |
6/21/23
|
7/1/23 |
$456 | Add |
|
Zac Lee | |||
|
Ext painting 002 Work Order 1047 |
6/21/23
|
7/1/23 |
$206 |
$30 |
|
Zac Lee | |||
|
Carpentry 002 Work Order 1047 |
6/21/23
|
7/1/23 |
$56 |
Add |
|
Zac Lee | |||
|
Power washing 001 Work Order 1047 |
6/21/23
|
7/1/23 |
$56 |
Add |
|
Zac Lee |
Project Communications
-
JohnHello, I'm John.
How can I help you today?08:55 -
08:56Hi, John
I need more information about Developer Plan.
Sam -
JohnAre we meeting today?
Project has been already finished and I have results to show you.08:57 -
08:59Well I am not sure.
I have results to show you.
Joyse -
JohnThe rest of the team is not here yet.
Maybe in an hour or so?08:57 -
08:59Have you faced any problems at the last phase of the project?
Jin -
JohnActually everything was fine.
I'm very excited to show this to our team.07:00
Photos
Project Progress Week 78%
Payment Chart
Project Schedule
-
Jan 04,2022 | 09:30Am
Mike Steele
Rotten Wood repair
-
Jan 06,2022 | 08:30Am
Schmidt Painting
Power Washing
-
Jan 07,2022 | 07:00Am
Gutter Monkeys
Remove Gutters
-
Jan 08,2022 | 08:30Am
Schmidt Painting
Prep Work
-
Jan 09,2022 | 08:00Am
Schmidt Painting
Painting Trim